Metal Roofing Permit in Miami, Florida: A Step-by-Step Guide

July 16, 2025

Installing a metal roof in Miami, Florida, is an excellent choice for durability and weather resistance, especially in a hurricane-prone area. However, a building permit is required to ensure compliance with the Florida Building Code and Miami-Dade County regulations. This guide outlines the process for obtaining a metal roofing permit from the City of Miami’s Building Department, with practical tips to make the process seamless.

Why You Need a Metal Roofing Permit in Miami

The City of Miami requires permits for all roofing work, including metal roof installations, to ensure safety, structural integrity, and compliance with the High-Velocity Hurricane Zone (HVHZ) standards mandated by the Florida Building Code in Miami-Dade County. Failing to obtain a permit can lead to fines, project delays, or complications during property transactions. Follow these steps to secure your permit efficiently.

Step-by-Step Guide to Obtaining a Metal Roofing Permit

1. Complete the Permit Application

Access the City of Miami’s digital permitting systems, ePlan or iBuild, through the City of Miami’s Permitting Services to start your application. Key details to include:

  • Property Information: Address and folio number (find it via the Miami-Dade County Property Appraiser).
  • Project Description: Specify “metal roofing installation” or similar.
  • Estimated Job Value: Total project cost, including materials and labor.
  • Signatures: Digital signatures from the property owner and a licensed contractor, if applicable.

2. Gather Required Documents

Prepare the following to accompany your application:

  • Proof of Ownership: A warranty deed or recent tax receipt.
  • Contractor’s License: Details of a Florida Certified Roofing Contractor (required unless you’re an owner-builder).
  • Owner/Builder Affidavit: Needed if you’re performing the work yourself, available via the City’s Permitting Forms.
  • Construction Documents: Include a site plan, roof framing plan, material specifications, and fastener details.
  • Miami-Dade Notice of Acceptance (NOA): Confirm that your metal roofing product is approved for HVHZ use in Miami-Dade County.
  • Roofing Inspection Report: A form to certify the roof’s condition, noting any deficiencies or required corrective measures.
  • Hurricane Mitigation Documentation: Details on secondary waterproofing, roof sheathing, and roof-to-wall connections, as required by Miami-Dade County’s Hurricane Mitigation Guidelines.

Check the City’s Permit Catalog for any additional requirements specific to your project.

3. Submit Your Application

Submit your application and documents digitally through the City of Miami’s ePlan or iBuild platforms. Alternatively, visit the Building Department at 444 SW 2nd Ave, Miami, FL 33130. You’ll receive a process number for tracking, and your plans will be routed for review.

4. Plan Review and Fees

The Building Department will review your application for compliance with the Florida Building Code and HVHZ standards. An upfront fee may be required at submission, with additional fees for reviews by Miami-Dade County departments (e.g., Fire, Environmental Resources, or Water and Sewer). The review process typically takes 24 hours to 10 business days, depending on project complexity and submission accuracy. Ensure all fees are paid promptly, as reviews won’t proceed until payment is confirmed.

5. Permit Approval and Issuance

Upon approval, you’ll be notified to pay the final permit fee via the City’s online portal. Once paid, you’ll receive a digital permit card, which must be displayed at the job site during construction.

6. Schedule Inspections

Inspections are required at various stages of the installation, including a final inspection to close the permit. Schedule inspections through the City’s online portal or by calling the Building Department at (305) 416-1100. Ensure compliance with HVHZ standards, such as proper fastening and secondary water barriers, to pass inspections.

Key Tips for a Smooth Permitting Process

  • Hire a Licensed Contractor: A Florida Certified Roofing Contractor can streamline the process by handling permitting and ensuring HVHZ compliance.
  • Owner-Builder Option: If acting as your own contractor, submit an Owner/Builder Affidavit and proof of ownership, but be prepared for stricter scrutiny.
  • Verify HVHZ Compliance: Use metal roofing panels with a valid Miami-Dade NOA to meet High-Velocity Hurricane Zone requirements.
  • Accurate Documentation: Double-check roof dimensions, slope, and product details to avoid delays or inspection failures.
  • Use Digital Tools: Leverage the City’s ePlan or iBuild systems for faster submission and tracking.

Summary of Permit Requirements

Requirement Details/Notes
Permit Application Submitted via ePlan or iBuild, signed by owner and contractor
Proof of Ownership Warranty deed or tax receipt
Contractor License Florida Certified Roofing Contractor (unless owner-builder)
Construction Documents Site plan, roof framing plan, material specs, NOA, and hurricane mitigation details
Submission Method Digital (ePlan/iBuild) or in person at 444 SW 2nd Ave, Miami, FL 33130
Review Time 24 hours to 10 business days (varies by complexity)
Inspections Required at multiple stages, including final inspection

Contact the City of Miami Building Department

For assistance or clarification, contact the City of Miami Building Department:

Conclusion

Obtaining a metal roofing permit in Miami, Florida, is a straightforward process when you follow these steps and leverage the City’s digital permitting tools. Whether you work with a licensed contractor or pursue the owner-builder route, ensuring compliance with HVHZ standards and local codes is essential for a successful project. Start your metal roofing installation by contacting a trusted contractor or the City of Miami Building Department today!

Need help with your roofing project? Reach out to the Building Department or a qualified roofing professional for guidance!